I think the deadline will be respected

The Minister of Transport says that the progress of the clearing works has reached 52%.

“This decision to partially close traffic between 6 am and 8 pm has led us to the situation we are in now, being halfway through the restricted period, let’s be with the works, I understand from the company, at 52% progress on this project, the deadline is August 9”, said Grindeanu.

He believes the deadline will be met.

“I believe, at this rate, that the works will be included in the assumed term. We were also lucky during these two weeks of relatively good weather, there were only one or two days of rain, which allowed us to work during these 14 hours with continuous fire,” added the Minister of Transport.

(source: AFP)

Source: jurnalul.ro